Computer Equipment: Process/Timeline for Purchasing

Process/Timeline for Purchasing Computing Equipment

Staff/Faculty Computer requests: review Staff/Faculty Computer Refresh Program information. 

For equipment falling outside of the guidelines linked above, please see below on how to start the purchase process. 

Computers/Docks (items that require configuration or network connectivity) 
Overall timeline: Typically 3.5-7.5 weeks. 

  • Requestor: Submit Computer/Equipment Purchase Approval Request
  • IT: Receive initial request
  • IT+Requestor: Requirements and/or specs definition/verification: 
    • 1-2 weeks, dependent on ability to coordinate with requestor
  • IT+Requestor: Infrastructure verification
    • 1:1 equipment replacement, N/A
    • One location: 1 week
    • Multiple locations: 2 weeks
  • IT: Requests quote from Purchasing
  • Purchasing: Provides a quote for
    • Standard spec items: 1-2 days
    • Non-standard spec items: 1-2 weeks
  • Processing time for PREQ:
    • 1 week
  • Once order submitted, approximate time to receive items in warehouse (if not backordered):
    • 1-2 weeks

Peripherals (Monitor, mice keyboard, webcams - items that do not require configuration or network connectivity) 
Overall timeline: Typically 3 weeks. 

  • Requestor: Submit Computer/Equipment Purchase Approval Request
  • IT: Process initial request
  • IT+Requestor: Requirements and/or specs definition/verification: 
    • 1 week
  • Purchasing: Turn around time to provide a quote for:
    • Standard spec items:1-2 days
    • Non-standard spec items:1-2 weeks
  • Processing time for PREQ:
    • 1 week
  • Once order submitted, approximate time to receive items in warehouse (if not backordered):
    • 1-2 weeks

Student Technology

  • Technology being loaned or distributed to students is purchased and managed through the CTC.

Software or Cloud Service Purchase Requests

  • Use this form to request approval of software and cloud services that have not been formally approved for use by the IT Dept.
  • New software purchases and purchases or renewals of cloud-based services are subject to Information Security review before they can be installed, renewed, and used.

IT Project Request

  • Use this form for submitting a new IT project. 
  • If you are wondering what an IT Project is, ask the following questions.
    • Is this a one-time task, or part of a bigger initiative?
    • Does it need planning, progress tracking, or teamwork?
    • Will it lead to a deliverable or a change in how our systems or software work?
  • If yes, it's likely a project.
  • If no, it's probably an operational task for TeamDynamix.